CAG flags delay in setting up Mumbai's Deonar waste-to-energy plant

The CAG report highlights a four-year delay in Mumbai's Deonar waste-to-energy plant project, leading to over 51.3 lakh tonnes of unprocessed waste at the site. It was awarded in Aug 2022, with completion expected in Oct. Meanwhile, the CAG praised Malkapur for its biogas and solar-powered compost plant, significantly reducing energy costs.
CAG flags delay in setting up Mumbai's Deonar waste-to-energy plant
MUMBAI: Flagging the delay in building a waste-to-energy plant at the 311-acre Deonar dumping ground, the comptroller and auditor general (CAG) said over 51.3 lakh tonnes of unprocessed waste accumulated at the landfill between 2016-17 and 2021-22.
The CAG report, which was tabled in the legislature on Wednesday, said the plant project was awarded in Aug 2022 after a four-year delay stemming from issues with pre-bid queries, geotechnical assessment and work order issuance, leaving waste unprocessed. "BMC planned to mitigate the environmental issues of open dumping at Deonar... by developing a waste-to-energy plant. However, the commissioning was not completed..." said the report that assessed data till Jan 2024.
Cag
BMC's executive engineer for solid waste management said the site development work, including pile foundation and compound wall, was in progress. "...Due to the delay in the award of the project and its completion, the municipal solid waste could not be converted into energy, and the entire waste continued to be dumped at the Deonar dumping ground."
While presenting BMC's 2025-26 budget in Feb, civic chief Bhushan Gagrani had said the plant would have the capacity to process 600 tonnes of waste and generate about 8MW of electricity daily. He had said its construction was underway and it is expected to be commissioned by this Oct.
The civic body had handed over 124 acres of the land to the state in Oct last year for housing under the Dharavi redevelopment project.
Meanwhile, the CAG report lauded Malkapur Municipal Council in Buldhana district for its biogas-powered compost plant and solar-powered facility, which cut energy costs by 68%, holding it as a model of sustainable waste management. "During joint physical verification... it was noticed that the entire energy requirement of a compost plant was met through a biogas plant that used segregated hotel wet waste for electricity generation.
This practice resulted in zero external energy consumption for operating the compost plant. Further, electricity generated from solar panels installed on a 2 tonne per day mechanical composting plant was used for operating the plant, thereby reducing energy charges by 68%."
author
About the Author
Richa Pinto

Richa Pinto is a special correspondent with The Times of India. She covers urban governance & climate change issues. With over a decade of experience in field reporting, she has written extensively on various civic issues affecting Mumbaikars. She graduated in -journalism from the prestigious Mumbai-based St Xavier's College and later pursued a three-year Law degree (L.L.B.) with the University of Mumbai. She regularly tweets about all things that matter to Mumbai on-- @richapintoi.

End of Article
FOLLOW US ON SOCIAL MEDIA